Challenge and approach
A 40-year plant was upgraded while shipments continued. The scope covered design, construction, qualification, and replies to the authority’s inspection questions.
Outcome: the agriculture-authority audit was passed.
Scope
- HVAC
- Cleanroom
- Bulk Gas
- C&Q
Duration
Construction 2 / Design to validation 5 months